MOUNT HOREB SCHOOL DISTRICT
Mount Horeb, WI
Overview
CLIENT
SQUARE FOOTAGE
Mount Horeb Area
School District
26,000 renovation
90,500 expansion
CLIENT SINCE
ARCHITECT
1961
Bray Architects
NUMBER OF PROJECTS
PROJECT DURATION
3
16 months





MOUNT HOREB SCHOOL DISTRICT
Renovation/Expansion
The Mount Horeb’s Middle and High School construction project included renovation of 26,000 square feet of the existing facility. The renovation process involved asbestos removal and was completed during the summer months while school was not in session. Construction of a 90,000 square foot addition with a new art commons area, ceramics classroom, woodworking shop and automobile and engine shop, stand-alone greenhouse was performed during the school year. This project required close coordination with the school administration to keep the grounds safe for students and staff while maintaining an efficient schedule.