Kraemer Brothers is Back at Catalent

Attention to detail at Catalent has been the most important factor in keeping the project flowing smoothly for our team and client. Due to the degree of importance in their lab work, Catalent has strict safety and clean room standards that must be met by Kraemer Brothers and our subcontractors at all times throughout the site. The protocols ensure the project creates minimal disruptions to Catalent’s production and most importantly, keeps all construction workers and Catalent employees safe. Within this 7,000 SF interior buildout area, crews will be setting the interior support steel for the new mezzanine and gantry, along with starting MEPs, in early March. Kraemer Brothers has also been remodeling the existing clean rooms we built in 2012. On the exterior 12,000 SF addition, structural steel work was completed as of February 24th, 2017.