Sauk County Highway Department Update

Both Sauk County Highway Department Buildings are starting to take shape. The new 164,000 square foot facility in Baraboo has finished up the exterior precast concrete wall panels. Currently, the bar joist, roof decking, and interior masonry non-bearing walls are being installed. Precast floor plank is scheduled to finish up soon while the precast roof plank will start middle of August. The slab-on-grade is set to be poured in August and continue into October. Steel stud framing, painting, storefronts, overhead doors, drywall, and MEP finishes will start after the concrete pours have finished.
The Reedsburg facility’s exterior precast wall panels have finished with structural steel, bar joist, metal decking, and interior masonry non-bearing walls, to start this month. Concrete topping and roofing will start in early August followed by the slab-on-grade pour in late August. Painting, MEP above ground rough-ins, tiling, storefronts, and overhead doors will follow the slab-on-grade pour, continuing into Fall. Both projects feature indoor fleet parking, wash bays, locker rooms, administrative offices, and plenty of storage space.